BiliranIsland.com Staff
BiliranIsland.com
First Posted 08:19:00
02/02/216
According to OIC GM Engr. Oledan, there is ongoing clearing of vegetation along Lemon portion going to Leyte2. Initial report from NGCP said 1 coco tree toppled down on 69 kV transmission line.
Brownout started around 1:58 am. Return of power not yet announced.
Power restored at 08:31 am today, 2 February.
– BiliranIsland.com
POWER UPDATEThe National Grid Corporation of the Philippines (NGCP) was unable to provide power to BILECO franchise…
Posted by Biliran ElectricCooperative on Monday, February 1, 2016