Above: P50M Construction of Access Road leading To Naval Port is on-going with pouring of concrete. Accomplishment as of December 31, 2017 is 16%. This project covers the entire street of Vicentillo. Vehicles are re-routed to certain streets and early warning devices and traffic personnel are present to provide safety and avoid traffic congestion within the town of Naval especially on Padre Inocentes Street. The project was prioritized because of the traffic congestion along this route during peak hours. Likewise, the existing concrete pavement shows deterioration, hence its prioritization under the FY 2017 DPWH Program.
Above: P50M Construction of Access Road leading To Naval Port is on-going with pouring of concrete. Accomplishment as of December 31, 2017 is 16%. This project covers the entire street of Vicentillo. Vehicles are re-routed to certain streets and early warning devices and traffic personnel are present to provide safety and avoid traffic congestion within the town of Naval especially on Padre Inocentes Street. The project was prioritized because of the traffic congestion along this route during peak hours. Likewise, the existing concrete pavement shows deterioration, hence its prioritization under the FY 2017 DPWH Program.

By: Chelsea Quijano- Salloman
DPWH Biliran

NAVAL, Biliran (BDEO) – The Department of Public Works and Highways (DPWH) – Biliran District Engineering Office (DEO) ends the year with 51.74% accomplishment surpassing its planned construction target of only 40.38%.

Based on its physical status report, BDEO has completed 49 out of its 57 FY 2017 projects with a positive slippage of 11.37%.

As of December 31, 2017, there were only eight projects remaining being fast-tracked for completion.

Engr. David P. Adongay, Jr., District Engineer reported that these projects were suspended due to the damage caused by Tropical Depression Urduja on December 15-16, 2017.

One of the on-going projects is the P172.192M Widening of Biliran Circumferential Road on six (6) road sections: Balaquid, Caray-caray, Burabod , Bool, Tucdao and Virginia which is the biggest project of Biliran DEO under FY 2017.

Another big project which is the P125.588M Widening along Biliran Circumferential Road is on-going with road sections at Culaba-Caibiran, Bilwang – Burabod, Sabang, Mapuyo and Kaulanguhan section.

Slope Protection along Biliran Circumferential Road at Sabang section, Tabunan Section and Buyo Section is also on-going along with the Construction of Slope Protection and a Widening Project at Naval-Caibiran Cross Country Road (NCCR).

Access Road Leading to Naval Port, Rehabilitation of Maripipi Circumferential Road and Off-carriageway Improvement along Biliran Circumferential Road is also being fast-tracked.
Adongay said that these remaining projects is target to be completed until March, 2018 if weather permits.

Comments

Previous articleP90.609-M Almeria Diversion Road Project finally realized
Next articleDamages in Biliran caused by TD Urduja and its restoration

LEAVE A REPLY

Please enter your comment!
Please enter your name here