NAVAL, Biliran –The construction of the new municipal building in the town of Caibiran is now on its finishing touches as the Department of Public Works and Highways (DPWH)- Biliran District Engineering Office inspects the project on September 28, 2022.

The said project is a three-clustered contract which involves construction of a 3-storey Caibiran Municipal Building with a total floor area of 3,259.75 sq.m; the construction of the Multi-Purpose Building (MPB), (Legislative Building), Phase II at Brgy. Palengke in the town of Caibiran and the construction of MPB (Legislative Building) at Brgy. Poblacion in Kawayan town.

This project is funded under the 2021 General Appropriations Act (GAA) with a revised contract amount of P39.16-M implemented by Chu Construction.

The project inspection was led by Engr. Luisito Filemon A. Abad, Chief of Construction Section together with Engr. Supremo Victor D. Sabitsana, Chief of Procurement Unit, Engr. Diolito S. Aberion, Project Engineer of BDEO, local media and project engineer of the contractor.

According to Engr. Abad, the said project is almost completed.

“As of now, almost completed na ang project, installation nalang ng air conditioning system ang kulang, so by 2nd week of October, tapos na siya”, said Engr. Abad.

The Chief of Construction Section explained that the project has its original completion date on January 29, 2022, however, it encountered delays in the implementation due to slight changes in plan as per request from the end-users and other aspects such as an unfavorable weather conditions and some restrictions brought about by Covid-19 pandemic.

According to Engr. Abad, the contractor has already secured a contract time extension and other pertinent documents which warrants the shortcomings.

The completion of the new municipal building will provide a spacious and a convenient workplace for the LGU employees which in return will give hassle-free transactions and a more quality service for the people of Caibiran.

Previous articleDPWH-BILIRAN DEO COMPLETES P42.9-M ASPHALT OVERLAY PROJECTS
Next articleDPWH-BDEO JOINS PUEBLO (CHARTER) DAY GRAND PARADE

LEAVE A REPLY

Please enter your comment!
Please enter your name here