#SeniangPH At 2:27 am, Dec 30 2014 the area coverage of BILECO lost power . Affected was the Milagro Tunga 69KV line.
|
December 22 and 23, 2014 Power Interruption Update:
A maximum of one hour and twenty minutes (1 hr 20 min.) power interruption was experienced in the entire Feeder 1 (Biliran-Naval-Almeria-Kawayan) last night, December 22, 2014 at around 7:50 PM due to the damaged bushing of the re-tapped Automatic Voltage Regulator (AVR) located in Sitio Camponggos, Bato, Biliran. Power was restored at around 9:10 PM.
A maximum of 42 minutes power interruption was experienced in the entire coverage area early today, December 23, 2014 at 4:23 AM due to the 69kv circuit breaker which tripped located at the Biliran Substation. Power was immediately restored in Feeder 2 at 4:24 AM, while in Feeder 1 power was restored up to Atipolo Exit at 4:50 AM and up to Mapuyo, Kawayan at 5:05 AM.
We are very sorry for the inconvenience. Hoping for the understanding of all member-consumers affected. - BILECO
#SeniangPH At 2:27 am, Dec 30 2014 the area coverage of BILECO lost power . Affected was the Milagro Tunga 69KV line.
A maximum three-hour (3-hr) power interruption will be experienced in the entire Feeder/Area 1 (Brgy. San Roque, Biliran-Naval-Almeria-Brgy. Mapuyo, Kawayan) on February 28, 2015, Friday, from 9:00 AM to 12:00 NN, due to the re-tapping of Automatic Voltage Regulator (AVR) in Sitio Campongos, Bato, Biliran.
SCHEDULE OF POWER INTERRUPTION ACTIVITIES (March 1-7, 2015)
1. A maximum seven-hour power interruption will be experienced in Brgy. Kawayanon, Caibiran on March 3, 2015, Tuesday, from 9:00 AM to 4:00 PM due to the replacement of rotten wood poles (3 J6 structures and 1 J10 structure) in said area.
2. A maximum seven-hour power interruption will be experienced in Brgy. Villa Vicenta, Caibiran on March 4, 2015, Wednesday, from 9:00 AM to 4:00 PM due to the replacement of rotten wood pole (J6 structure) and clustering of kilowatt-hour meters (kwhm) in said area.
3. A maximum seven-hour power interruption will be experienced in Brgy. Cabibihan, Caibiran on March 5, 2015, Thursday, from 9:00 AM to 4:00 PM due to the replacement of rotten wood pole (J10 structure) and clustering of kilowatt-hour meters (kwhm) in said area.
4. A maximum four-hour (4-hr) power interruption will be experienced in Brgy. Bunga (exit), Cabucgayan up to Brgy. Villa Cornejo, Kawayan on March 6, 2015, Friday, from 10:00 AM to 2:00 PM due to the installation of Oil Break Switch in Brgy. Bunga, Cabucgayan. - BILECO
BILECO Power Update: max 8-hr power outage wl b experienced in the entire Area 1 (Biliran-Naval-Almeria-Kawayan) on Mar. 15,9:30am-5:30pm due 2 d installation & commissioning of new AVR in Campongos,Bato,Biliran.
Gipasabot sa Biliran Electric Cooperative, Inc. ang mga Miyembro-Konsumedor sa distrito sa Caibiran na adunay usa ka aplikante nga ning-kwalipikar isip pagka-director sa umaabot nga regular district election karong Marso 21, 2015.
Power Update:
NOTICE TO MEMBER-CONSUMERS
SCHEDULE OF POWER INTERRUPTION ACTIVITIES FOR AREA 1 and Area 2 (September 7-11, 2015)
1. A maximum eight-hour (8-hour) power interruption will be experienced in the entire coverage of Brgy. Burabod and Brgy. Mapuyo, Kawayan on September 9, 2015, Wednesday, from 9:00 AM to 5:00 PM, due to the upgrading of Open Secondary line to Single Phase line in Brgy. Mapuyo, Kawayan.
2. A maximum eight-hour (8-hour) power interruption will be experienced in Brgy. Esperanza, Cabucgayan on September 9, 2015, Wednesday, from 9:00 AM to 5:00 PM, due to the replacement of 2 decaying wood poles Single-phase, twisted secondary wires and re-clustering of KWH meter in said area.
3. A maximum eight-hour (8-hour) power interruption will be experienced in entire coverage of Brgy. Inasuyan to Brgy. Villa Cornejo, Kawayan on September 10, 2015, Thursday, from 9:00 AM to 5:00 PM, due to the upgrading of Open Secondary line in Brgy. Ungale, Kawayan.
4. A maximum seven-hour (7-hour) power interruption will be experienced in Sitio Tubig, Inasuyan to Villa Cornejo Kawayan on September 10, 2015, Thursday, from 9:00 AM to 4:00 PM, due to the upgrading of single phase line to 2-phase line and tapping of new 2-phase line in Brgy. Ungale, Kawayan.
5. A maximum eight-hour (8-hour) power interruption will be experienced in whole coverage of Brgy. Bari-is, Caibiran on September 11, 2015, Friday, from 9:00 AM to 5:00 PM, due to the replacement of 2 decaying wood poles and re-clustering of KWH meter in said area.
6. A maximum five-hour (5-hour) power interruption will be experienced in Sitio Agta, Brgy. Talahid, Almeria on September 11, 2015, Friday, from 9:00 AM to 2:00 PM, due to tha tapping of Single Phase line of Talahid beach.
Hoping for the understanding of all member-consumers affected. Kindly disseminate information. Thank you.
The National Grid Corporation of the Philippines (NGCP) will be interrupting power service to BILECO franchise for a maximum of 10 hours on September 19, 2015, Saturday, between 7:00 AM to 5:00 PM due to the shutting down of 100MVA Transformer 5, Ormoc SS and 69kV Lemon – Biliran TL
![]()
BILECO POWER UPDATE: SCHEDULE OF POWER INTERRUPTION ACTIVITIES for Area 1 and Area 2 (January 11-16, 2016)
1. A maximum ONE-HOUR and THIRTY-MINUTE (1-HR & 30-MIN) power interruption will be experienced in BRGY. BOOL EAST, BOOL WEST and BOOL CENTRAL, CULABA on JANUARY 12, 2016, TUESDAY, from 9:30 to 11:00 AM due to the installation of additional transformer for the upcoming fiesta celebration and KWH meter clustering in said areas.
2. A maximum NINE-HOUR (9-HR) power interruption will be experienced in Area 1 starting from BERNARDES I, ATIPOLO, NAVAL going to BRGY. MAPUYO, KAWAYAN on JANUARY 13, 2016, WEDNESDAY, from 7:00 AM to 4:00 PM due to the relocation/transfer of 3-phase line to new pole in Brgy. Agpangi, Naval.
3. A maximum SEVEN-HOUR (7-HR) power interruption will be experienced in SITIO BANACOD, BRGY. VICTORY, CAIBIRAN on JANUARY 15, 2016, FRIDAY, from 9:00 AM to 4:00 PM due to the replacement of rotten wood pole in said area.
4. A maximum FOUR-HOUR (4-HR) power interruption will be experienced starting from BRGY. CASIAWAN up to BRGY. CAANIBUNGAN, CABUCGAYAN on JANUARY 14, 2016,THURSDAY, from 8:00 AM to 12:00 PM due to the tapping of new lines in said areas.
5. A maximum FOUR-HOUR (4-HR) power interruption will be experienced in SAN JUAN, LUCSOON, BRGY. LICO, BRGY. P.S. EAMIGUEL, BRGY. IMELDA, BRGY. CAPIÑAHAN AND BRGY. VILLACONSUELO, NAVAL on JANUARY 16, 2016, SATURDAY, from 8:00 AM to 12:00 PM due to the tapping of new lines in said areas.
BILECO POWER UPDATE
SCHEDULE OF POWER INTERRUPTION ACTIVITIES for Area 1 and Area 2 (January 25-29, 2016)
1. A maximum SIX-HOUR (6-HR) power interruption will be experienced in PART OF BRGY. BUSALI, BILIRAN on JANUARY 25, 2016, MONDAY, from 9:00 AM to 3:00 PM due to the replacement of decaying woodpole in Brgy. Busali, Biliran.
2. A maximum SIX-HOUR (6-HR) power interruption will be experienced in BRGY. ESPERANZA, CABUCGAYAN on JANUARY 25, 2016, MONDAY, from 10:00 AM to 4:00 PM due to the replacement of open secondary line in said area.
3. A maximum TWO-HOUR (2-HR) power interruption will be experienced in BRGY. TAMARINDO, BRGY. IYUSAN & BRGY. SALANGI, ALMERIA on JANUARY 26, 2016, TUESDAY, from 1:00 to 3:00 PM due to the installation of cut-out in Sitio Briquiting, Tamarindo, Almeria under the NEA SEP 2015.
4. A maximum SEVEN-HOUR (7-HR) power interruption will be experienced in PART OF BRGY. STO. NIÑO, NAVAL on JANUARY 26, 2016, TUESDAY, from 9:00 AM to 4:00 PM due to the meter clustering in Brgy. Sto. Niño, Naval.
5. A maximum SIX-HOUR (6-HR) power interruption will be experienced in BRGY. UNGALE, KAWAYAN on JANUARY 26, 2016, TUESDAY, from 10:00 AM to 4:00 PM due to the replacement of primary lines in said area.
6. A maximum SIX-HOUR (6-HR) power interruption will be experienced in SITIO PICAS, BRGY. MAGBANGON, CABUCGAYAN on JANUARY 27, 2016, WEDNESDAY, from 10:00 AM to 4:00 PM due to the replacement of lateral line in said area.
7. A maximum SEVEN-HOUR (7-HR) power interruption will be experienced in PART OF CANEJA STREET, CORNER BALLESTEROS, SABENORIO, MAGALLANES & CASTIN STREETS, BRGY. SMO. ROSARIO, NAVAL on JANUARY 28, 2016, THURSDAY, from 9:00 AM to 4:00 PM due to the replacement of decaying woodpole & meter clustering in Caneja Street, Brgy. Smo. Rosario, Naval.
8. A maximum SIX-HOUR (6-HR) power interruption will be experienced in BRGY. ALEGRIA & BRGY. BINOHANGAN, CAIBIRAN on JANUARY 28, 2016, THURSDAY, from 10:00 AM to 4:00 PM due to the replacement of primary lines in Brgy. Alegria, Caibiran.
9. A maximum SEVEN-HOUR (7-HR) power interruption will be experienced in PART OF BRGY. ATIPOLO, NAVAL on JANUARY 29, 2016, FRIDAY, from 9:00 AM to 4:00 PM due to the meter clustering in Brgy. Atipolo, Naval.
10. A maximum SIX-HOUR (6-HR) power interruption will be experienced in BRGY. CANILA, BILIRAN on JANUARY 29, 2016, FRIDAY, from 10:00 AM to 4:00 PM due to the replacement of open secondary line in said area.