Ongoing Concrete Paving of Biliran
Ongoing Concrete Paving of Biliran Circumferential Road, km 1089+100 1096 + 640 w/ exceptions (San Agustin - Pawikan Road Section). Biliran Province Photo by Jalmz
CONTRACTOR: The Tuscan Structures and Supplies
DATE STARTED: Feb. 7, 2013
DURATION: 180 C. D.
CONTRACT COMPLETION DATE: August 5, 2013
CONTRACT COST: Php 43,665,409.49
CONSTRUCTION CONSULTANT:
IMPLEMENTING OFFICE: DPWH Biliran
SOURCE OF FUND: SARO # ABM - ROVIII -13- 0003601 dtd. 01-02-13
CONTRACTOR: The Tuscan Structures and Supplies
DATE STARTED: Feb. 7, 2013
DURATION: 180 C. D.
CONTRACT COMPLETION DATE: August 5, 2013
CONTRACT COST: Php 43,665,409.49
CONSTRUCTION CONSULTANT:
IMPLEMENTING OFFICE: DPWH Biliran
SOURCE OF FUND: SARO # ABM - ROVIII -13- 0003601 dtd. 01-02-13